Renovations Are Done And Dusted

Once the dust had settled, and the pain of having builders in private spaces for too long had faded, the inevitable questions arose. Why were these wonderful alterations not made years ago? And why did we not move out while work was in progress?

Both answers in this case undoubtedly relate to the marvellous benefits of working at home. None of which of course applied during the nine weeks of what was considered minor renovations. By then, favourite expressions like cost savings, flexibility, accessibility, peace and quiet, and no commuting, had become distant memories.

Another stark reality is that modern renovations in older houses hold many surprises. Contemporary designs and aesthetics do not necessarily sit well with antiquated electrics, plumbing or building methods. As a result, what started with good intentions on a wet winter’s morning, ended in a sigh of relief when the house was vacated, six weeks later than originally planned.

More than one dear lesson was learnt, notwithstanding the capabilities and obliging manner of the appointed building team, who occupied the guest suite from an outside back entrance so to avoid foot traffic through other living areas. Other than a speedy acquaintance with building supply stores, and tongue twisting plumbing terminology, what really matters is paying attention to detail during actual building proceedings.

However, despite several building mistakes which required rectification caused delays, there is nothing quite as pleasant as seeing a family appreciate greater functionality and comfort in their home. After starting out as two naive homeowners on a maiden voyage into the world of building, we gained a fortune of knowledge with greater appreciation for the building trade.

What causes delays in renovation projects?

Poorly communicated procedures

Contractors over committing themselves on managing different projects simultaneously

Building industry strikes

Ill health of project managers and staff

Weather conditions impacting on curing of surfaces

Stock shortages at suppliers

Why do building schedules and sequence of events need to be communicated?

Owners and builders need to co-ordinate ordering and deliveries of fittings, finishes and materials

To determine periods when certain living areas become inaccessible

To provide storage space for house contents

To retain functionality of at least one bathroom and kitchen tap at all times

Different fittings take place at various stages

Preparation is not to be underestimated

Allow sufficient time for clearing, packing and storage before builders arrive

Plan and manage excessive dust

Daily covering and cleaning of work surfaces with builders’ own equipment, including vacuum cleaner

Agree on exterior work and tap areas such as for mixing cement

Allocate under cover storage space for large items including scaffolding

Discuss storage and access of new deliveries as well as removed items

Ensure regular rubble removals to a registered site

Anticipate unexpected shopping expeditions

Supervision aids cost management

Daily consultations, progress reports, and plans between owners and supervisors

Stay within budget

Manage variations to order, progress payments and compare with original quotations

Before signing off, check original job descriptions which may impact on costing

Delays and remedies

Incorrect positioning of shower plumbing - removal, refitting, re-plastering and curing

Shattered shower enclosure - re-ordering and re-fitting by shower specialist

Incorrect building angle of shower lip for flow-off - re-building, re-tiling and re-fitting of edge trim

Broken window – slow crack caused during installation noted after sign off – self replacement and installation

Accidental dog paws through wet floor screed – manual sanding process

Most important lessons learnt

Anticipate unexpected extra costs

Cover everything irrespective of ‘no dust’ promises

Prevent sewerage blockages resulting from disposal of building materials

Obtain proof of National Builders Association South Africa registration

Finally, well managed renovations are worth the discomfort, and not quite true to the old saying: “May you have builders for the rest of your life.”

Related Articles

Neighbourhood focus: Brooklyn, Pretoria
Private Property Reporter | 03 Jul 2025

Neighbourhood focus: Brooklyn, Pretoria

A top Pretoria suburb, Brooklyn blends prestige, student life, and family charm with diverse real estate options.

The ultimate property viewing checklist
Private Property Reporter | 02 Jul 2025

The ultimate property viewing checklist

First-time home buyer? Spot property red flags early with this essential checklist for first-time buyers.

10 mistakes first-time buyers make and how to avoid them
Private Property Reporter | 01 Jul 2025

10 mistakes first-time buyers make and how to avoid them

When seeking a home for the first time, the options can be overwhelming and confusing. These are the 10 most frequent mistakes you should avoid.

sample image of property alerts

Get instant property alerts

Be the first to see property alerts for your area.

Create an account or log in

Receive personalised property alerts and so much more!

By continuing you accept Private Property’s Terms & Conditions and Privacy Policy.

Cookie Preferences
Property Alert Created!
Success
Your alert was successfully created.

Your Privacy

By clicking Accept all cookies you agree to use all cookies to help improve your experience with personalised content. Or click Cookie preferences to change cookies or withdraw consent.

;